Second stretch of Rail Corridor to be closed on 19 September

$
0
0

The second stretch of the Rail Corridor being affected by the Murnane Pipeline Project, which extends from Commonwealth Ave all the way southwards to Tanjong Pagar Railway Station, is being closed to the public from 19 September 2016.

A section within the stretch, from Jalan Kilang Bahru to Tanjong Pagar, will remain closed until the pipe laying project is completed. Its reopening is scheduled for the fourth quarter of 2019.

One of the stretches affected, at Tanglin Halt, during the days of the railway.

Part the stretch to be closed at Tanglin Halt, seen in the days of the railway.

Work has already commenced in the initial  section that was closed. The final section affected, from Jalan Anak Bukit to Holland Road, will close later this year.

Beside the closures affecting the Rail Corridor, work on the final stretch of the MRT’s Circle Line will see Tanjong Pagar Railway Station closed from next year. The station, under which the MRT line is being run, will only reopen in 2025. Updates on the Murnane Pipeline Project, and on the closure and reopening of the affected stretches, kindly visit the PUB Facebook Page.

Schedule for closure of the southern stretch of the Rail Corridor (click to expand).


Filed under: Changing Landscapes, Forgotten Places, Queenstown, Rail Corridor, Railway Land, Singapore, Tanjong Pagar